Deal on Church Could Speed Ground Zero Rebuilding

Deal on Church Could Speed Ground Zero Rebuilding

Jul 11, 2008
By By: Peter Kiefer | NY Sun | New York Sun

The executive director of the Port Authority, Christopher Ward, told the local Community Board 1 last night that an agreement with the leaders of St. Nicholas Greek Orthodox Church for an exchange of land needed to provide the congregation with a new home near ground zero had been reached. The church was destroyed after the terrorist attacks of September 11, 2001, when the World Trade Center’s South Tower collapsed and obliterated the building.

Mr. Ward later clarified his comments to reporters, saying, “We are finalizing an agreement and I would expect it to be done soon.”

The inability to strike a deal with the church has impeded the Port Authority from building the 16-acre site’s southern foundation wall and finalizing designs for an underground security screening center. Negotiations stalled over the funding for and exact location of the new church.

Mr. Ward was joined at the hearing by the deputy mayor for economic development, Robert Lieber, the president of World Trade Center Properties, Janno Lieber, the chairman of the Lower Manhattan Development Corp., Avi Schick, the president of the World Trade Center Memorial Foundation, Joseph Daniels, and the president of the Lower Manhattan Construction Command Center, Robert Harvey, who were answering questions from residents and members of the community board about delays at the site.

Also on hand for the meeting was the Assembly speaker, Sheldon Silver.

The president of Community Board 1, Julie Menin, presented the officials with 10 demands, including that the community board and local residents be provided with a list of realistic deadlines for reconstruction, to be answered by September 30.

Following the meeting Ms. Menin said she was pleased with the candor of the responses. “I was happy to see for the first time I have ever seen since I have been involved in the rebuilding of Lower Manhattan that people actually said no. There were some emphatic nos, and that is the right answer because one of the things that has stymied the rebuilding process has been too many platitudes, and too many unrealistic deadlines.”

 

Terms of Use

Copyright License

Use of this Website is subject to the terms of this disclaimer and by using the Website, you agree to these terms. Silverstein Properties, Inc. ("Silverstein") publishes this Website solely for general informational purposes and nothing herein is intended to be an offer of property, or leasehold or goods or services or employment or a representation as to property, or leasehold or goods or services or employment that will be provided to any person. Silverstein obtains some of the information on the Website from third parties and makes reasonable efforts to provide accurate information on the website. However, it cannot guarantee its accuracy and under no circumstances will it be responsible for inaccuracies whether in material provided by Silverstein or obtained from third parties. The information contained herein may change without notice. The information contained herein will only be considered a representation of Silverstein if repeated in a final contract signed by an authorized Silverstein representative.

Disclaimer

Silverstein Properties, Inc. grants to you a limited non-exclusive, non-transferable license to view, copy and print the material on this web site (other than the design or layout of this Website) for your non-commercial or personal use only. All copies that you make must retain all copyright and other notices that are on this Website. Otherwise, you may not use, distribute, sell, modify, transmit, revise, reverse engineer, republish, post or create derivative works of the material on this Website without Silverstein Properties, Inc.'s prior written permission in each instance.

© Silverstein Properties, Inc., all rights reserved except as expressly provided elsewhere on this Website.