WTC Construction Update, November 2008

WTC Construction Update, November 2008

Nov 08, 2008
By By: LowerManhattan.info |

The following lists the major work taking place currently at the site:

Freedom Tower:

  • Installation of tower-foundation steel columns (two cranes on site)
  • Installation of tower-foundation steel columns (two cranes on site); superstructure reached grade in July 2008
  • Pouring concrete for the foundation and rebar installation for core and sheer wall
  • Utility installation and tie-ins

 

WTC East Bathtub:

  • Excavation of the Tower Two site through October 2008; crews are working double shifts
  • Concrete pours began at the Tower 4 site in July 2008
  • Major excavation of the south half of the east bathtub (sites of Towers Three and Four) from July 2007 through February 17, 2008; Silverstein Properties’s construction team is mobilized and preliminary construction is underway
  • Structural support and excavation under the 1 train box, which runs through the WTC site along Greenwich Street

National September 11th Memorial and Museum:

  • Slurry wall reinforcement
  • The “Survivors Stairway” will be relocated to its permanent home in the underground Memorial by late 2008
  • Steel installation began September 1, 2008
  • Concrete installation begins in early 2009
  • Memorial crews plan to remove the ramp into the WTC site by December 2008 to continue construction on the south footprint
  • The World Trade Center Memorial Foundation announced on April 9, 2008 that it reached its $350 million private fundraising goal

 

Tower 4

  • Excavation
  • Foundation work including concrete pours

Tower 3

  • Excavation; rock blasting through fall 2008 
  • Foundation work 

130 Liberty Street/Deutsche Bank Building Deconstruction:

  • Abatement crews are currently working downward
  • Full decontamination is underway as of May 2008

Air-quality testing at the building continues, with 12 sampling sites in the building’s immediate vicinity. Air monitoring reports are available here; more information about air monitoring is available here and on the LMDC’s website.

Source: LowerManhattan.info 

 

Terms of Use

Copyright License

Use of this Website is subject to the terms of this disclaimer and by using the Website, you agree to these terms. Silverstein Properties, Inc. ("Silverstein") publishes this Website solely for general informational purposes and nothing herein is intended to be an offer of property, or leasehold or goods or services or employment or a representation as to property, or leasehold or goods or services or employment that will be provided to any person. Silverstein obtains some of the information on the Website from third parties and makes reasonable efforts to provide accurate information on the website. However, it cannot guarantee its accuracy and under no circumstances will it be responsible for inaccuracies whether in material provided by Silverstein or obtained from third parties. The information contained herein may change without notice. The information contained herein will only be considered a representation of Silverstein if repeated in a final contract signed by an authorized Silverstein representative.

Disclaimer

Silverstein Properties, Inc. grants to you a limited non-exclusive, non-transferable license to view, copy and print the material on this web site (other than the design or layout of this Website) for your non-commercial or personal use only. All copies that you make must retain all copyright and other notices that are on this Website. Otherwise, you may not use, distribute, sell, modify, transmit, revise, reverse engineer, republish, post or create derivative works of the material on this Website without Silverstein Properties, Inc.'s prior written permission in each instance.

© Silverstein Properties, Inc., all rights reserved except as expressly provided elsewhere on this Website.