Construction is well underway at the World Trade Center site in Downtown Manhattan. The following lists the major work taking place currently at the site:

Tower Three:
• Excavation
• Preparations for foundation work

Tower Four:
• Excavation
• Preparations for foundation work

Freedom Tower:
• Installation of tower-foundation steel columns (two cranes on site) 
• Pouring concrete for the foundation and rebar installation for core and sheer wall 
• Utility installation and tie-ins

East Bathtub:
• Major excavation of the south half of the east bathtub (sites of Towers Three and Four) from July 2007 through February 17, 2008; Silverstein Properties’s construction team is mobilized and preliminary construction is underway 
• Excavation of the Tower Two site through June 30, 2008; crews began working double shifts in February 2008 
• Installation of mini-piles continues around the 1 train box, which runs through the WTC site along Greenwich Street 
• Slurry wall installation was completed in mid-May 2007 in the bathtub’s south half; installation of tiebacks took place through late 2007

Memorial:
• Slurry wall reinforcement 
• Cassions and mini-piles installation was completed March 2008 
• The “Survivors Stairway” was relocated from its original location to the west side of the WTC site, to be incorporated into the underground Memorial by 2009 
• The first steel erected in the north footprint in winter 2008 
• Memorial crews plan to remove the ramp into the WTC site in summer 2008 to continue construction on the south footprint 
• The World Trade Center museum and memorial complex has reached its private fundraising goal of $350 million, its board of directors announced April 9

Terms of Use

Copyright License

Use of this Website is subject to the terms of this disclaimer and by using the Website, you agree to these terms. Silverstein Properties, Inc. ("Silverstein") publishes this Website solely for general informational purposes and nothing herein is intended to be an offer of property, or leasehold or goods or services or employment or a representation as to property, or leasehold or goods or services or employment that will be provided to any person. Silverstein obtains some of the information on the Website from third parties and makes reasonable efforts to provide accurate information on the website. However, it cannot guarantee its accuracy and under no circumstances will it be responsible for inaccuracies whether in material provided by Silverstein or obtained from third parties. The information contained herein may change without notice. The information contained herein will only be considered a representation of Silverstein if repeated in a final contract signed by an authorized Silverstein representative.

Disclaimer

Silverstein Properties, Inc. grants to you a limited non-exclusive, non-transferable license to view, copy and print the material on this web site (other than the design or layout of this Website) for your non-commercial or personal use only. All copies that you make must retain all copyright and other notices that are on this Website. Otherwise, you may not use, distribute, sell, modify, transmit, revise, reverse engineer, republish, post or create derivative works of the material on this Website without Silverstein Properties, Inc.'s prior written permission in each instance.

© Silverstein Properties, Inc., all rights reserved except as expressly provided elsewhere on this Website.